Time and Work, Pipes and Cisterns (Aptitude #9)

Time and work is really a rate problem: if A finishes a job in \(x\) days, A’s rate is \(\frac{1}{x}\) of the job per day, and combined rates add. Pipes and cisterns are the same problem with filling instead of working, and an outlet pipe is a negative rate. This post works every variation.

The core idea

\[ \text{Work rate} = \frac{1}{\text{time}}, \qquad \text{Work done} = \text{Rate} \times \text{Time} \]

If A alone takes \(x\) days and B alone takes \(y\) days, together they take:

\[ T = \frac{xy}{x + y} \text{ days} \]

Variation 1 — combined work

Q. A can do a job in 12 days and B in 18 days. How long together? Solution. \(T = \frac{12 \times 18}{12 + 18} = \frac{216}{30} = 7.2\) days.

Variation 2 — find one person’s time given the combined time

Q. A and B together finish in 6 days; A alone takes 10 days. How long does B take? Solution. B’s rate \(= \frac16 - \frac{1}{10} = \frac{5-3}{30} = \frac{2}{30} = \frac{1}{15}\), so B takes 15 days.

Variation 3 — work in stages

Q. A can do a job in 10 days, B in 15 days. They work together for 4 days, then A leaves. How long does B take to finish? Solution. Combined rate \(= \frac{1}{10} + \frac{1}{15} = \frac{1}{6}\). In 4 days they do \(\frac{4}{6} = \frac{2}{3}\). Remaining \(= \frac{1}{3}\). B’s rate \(= \frac{1}{15}\), so time \(= \frac{1}{3} \times 15 = 5\) days.

Variation 4 — alternate-day work

Q. A does a job in 6 days, B in 12 days. They work on alternate days with A starting. In how many days is the job done? Solution. Two days’ work \(= \frac{1}{6} + \frac{1}{12} = \frac{1}{4}\). So every 2 days they do \(\frac14\). After 4 cycles (8 days) they have done 1. Actually \(\frac{3}{4}\) in 6 days; day 7 is A’s: \(\frac{3}{4} + \frac{1}{6} = \frac{11}{12}\); day 8 is B’s: \(\frac{11}{12} + \frac{1}{12} = 1\). Done in 8 days.

Variation 5 — three workers

Q. A, B, C can do a job in 6, 8, and 12 days. How long together? Solution. Combined rate \(= \frac16 + \frac18 + \frac1{12} = \frac{4+3+2}{24} = \frac{9}{24} = \frac{3}{8}\). Time \(= \frac{8}{3} = 2\tfrac{2}{3}\) days.

Variation 6 — efficiency ratios

If A is twice as efficient as B, A takes half the time. Rates are in the ratio of efficiencies.

Q. A is twice as good a workman as B, and together they finish in 14 days. Find A’s alone time. Solution. Let B’s time be \(2x\), A’s \(x\) (rates \(1/x\) and \(1/2x\)). Combined rate \(= \frac{1}{x} + \frac{1}{2x} = \frac{3}{2x} = \frac{1}{14} \Rightarrow 2x = 42 \Rightarrow x = 21\). A alone takes 21 days (B 42).

\begin{tikzpicture}[font=\rmfamily, >=stealth,
  b/.style={draw, thick, minimum width=1.4cm, minimum height=0.55cm, font=\small\ttfamily},
  a/.style={->, thick}]
  \node[b, fill=blue!10] (A) at (0,1.0) {A: 1/6 per day};
  \node[b, fill=green!14] (B) at (0,0.2) {B: 1/12 per day};
  \node[b, fill=orange!18] (C) at (0,-0.6) {combined: 1/6 + 1/12};
  \draw[a] (A.south) -- (C.north); \draw[a] (B.south) -- (C.north);
  \node[font=\rmfamily\small, text=black!60, anchor=west] at (1.5,-0.2) {rates add};
\end{tikzpicture}

Pipes and cisterns

An inlet pipe fills (positive rate); an outlet pipe empties (negative rate). Everything else is identical to time and work.

Variation 7 — two inlets

Q. One pipe fills a tank in 4 hours, another in 6 hours. How long to fill together? Solution. Combined rate \(= \frac14 + \frac16 = \frac{5}{12}\); time \(= \frac{12}{5} = 2.4\) hours.

Variation 8 — inlet and outlet

Q. A pipe fills a tank in 10 hours; a leak empties it in 15 hours. How long to fill with both open? Solution. Net rate \(= \frac{1}{10} - \frac{1}{15} = \frac{1}{30}\); time \(= 30\) hours.

Variation 9 — pipe closed partway

Q. Two pipes fill in 12 and 15 hours. Both opened; the first is closed after 4 hours. How long to finish? Solution. In 4 hours: \(4\left(\frac1{12} + \frac1{15}\right) = 4 \times \frac{9}{60} = \frac{3}{5}\). Remaining \(= \frac{2}{5}\); second pipe rate \(= \frac1{15}\); time \(= \frac{2}{5} \times 15 = 6\) more hours. Total \(= 10\) hours.

Work and wages

Wages are shared in proportion to work done (rate × time) or, for equal time, to efficiency.

Q. A, B, C together earn ₹2,000 for a job; A works 6 days, B 8, C 10 and they have equal efficiency. Find each share. Solution. Ratio \(= 6:8:10 = 3:4:5\); parts \(= 12\); A \(= ₹500\), B \(= ₹666.67\), C \(= ₹833.33\).

The \(M_1 D_1 / W_1\) formula

For men, days, hours, and work:

\[ \frac{M_1 D_1 H_1}{W_1} = \frac{M_2 D_2 H_2}{W_2} \]

Q. 12 men do a job in 8 days. How many men finish 3 times the work in 6 days? Solution. \(\frac{12 \times 8}{1} = \frac{M \times 6}{3} \Rightarrow 96 = 2M \Rightarrow M = 48\).

Shortcuts worth memorising

Practice

QQuestionA and B can do a job in 12 days; B and C in 15 days; A and C in 20 days. How long for A, B, C together?

[!solution] Adding: \(2\left(\frac1A+\frac1B+\frac1C\right) = \frac1{12}+\frac1{15}+\frac1{20} = \frac{5+4+3}{60} = \frac{12}{60} = \frac15\). So combined rate \(= \frac1{10}\), time \(= **10 days\)**.

QQuestionA can do a job in 20 days, B in 30. They work together for 5 days; A leaves. How long does B take to finish?

[!solution] Combined rate \(= \frac1{20}+\frac1{30} = \frac1{12}\). In 5 days \(= \frac5{12}\). Remaining \(\frac7{12}\); B’s time \(= \frac7{12} \times 30 = **17.5 days\)**.

QQuestionTwo pipes fill a tank in 6 and 8 hours; a drain empties it in 12. All open — how long to fill?

[!solution] Net rate \(= \frac16 + \frac18 - \frac1{12} = \frac{4+3-2}{24} = \frac5{24}\); time \(= **4.8 hours\)**.

QQuestion20 men can build a wall in 15 days. How many men are needed to build it in 10 days?

[!solution] \(20 \times 15 = M \times 10 \Rightarrow M = **30 men\)**.

Pitfalls

QQuestionSelf-check

How do you combine two workers’ times, and how do you handle an emptying pipe?

ASolution

Add their rates (\(1/x + 1/y\)) and take the reciprocal, \(\frac{xy}{x+y}\). An emptying pipe subtracts its rate, so net rate \(= \frac1{\text{inlet}} - \frac1{\text{outlet}}\).

Next: Permutations, Combinations and Probability (Aptitude #10) — counting arrangements.